Project Status
Updated
last on July 27, 2006
|
|
Projected Time |
2410.2 |
13.6% |
|
|
|
Start |
Finish |
Duration |
|
|
Chapter
4 |
10/1/2005 |
1/28/2006 |
92.45 |
149.1% |
|
Step 1 |
10/1/2005 |
1/24/2006 |
12.70 |
|
|
Step 2 |
10/2/2005 |
10/23/2005 |
17.00 |
|
|
Step 3 |
10/12/2005 |
11/3/2005 |
23.00 |
|
|
Step 4 |
11/2/2005 |
11/16/2005 |
24.25 |
|
|
Step 5 |
11/29/2005 |
1/28/2006 |
15.50 |
|
|
Chapter
5 |
12/2/2005 |
1/28/2006 |
74.75 |
113.3% |
|
Step 1 |
12/2/2005 |
12/19/2005 |
8.00 |
|
|
Step 2 |
12/19/2005 |
12/30/2005 |
22.75 |
|
|
Step 3 |
12/29/2005 |
12/31/2005 |
4.00 |
|
|
Step 4 |
12/30/2005 |
1/3/2006 |
16.00 |
|
|
Step 5 |
1/6/2006 |
1/13/2006 |
11.00 |
|
|
Step 6 |
1/13/2006 |
1/28/2006 |
13.00 |
|
|
Chapter
6 |
1/28/2006 |
5/4/2006 |
121.00 |
144.0% |
|
Step 1 |
1/28/2006 |
5/4/2006 |
56.00 |
|
|
Step 2 |
3/18/2006 |
4/8/2006 |
27.50 |
|
|
Step 3 |
4/9/2006 |
4/29/2006 |
37.50 |
|
|
Chapter
7 |
5/7/2006 |
|
38.50 |
67.5% |
|
Step 1 |
5/7/2006 |
6/29/2006 |
13.50 |
|
|
Step 2 |
5/25/2006 |
7/7/2006 |
13.50 |
|
|
Step 3 |
7/15/2006 |
|
11.50 |
|
|
Step 4 |
|
|
0.00 |
|
|
Step 5 |
|
|
0.00 |
|
Construction
is currently in Chapter 7 - Fuselage Exterior