May 1 - Brick delivered and all the windows installed
May 2, 3, 6 - Finishing work done on the inside walls (final adjustments to
walls/door openings)
May 7 - Tar paper put on roof, electrical work begun (installation of outlet and
light switch boxes)
May 8 - Showers and bathtubs delivered, fireplace installed, plumbing completed,
most outlets/lights/switch boxes installed, most wiring run. (a busy day!)
May 9 - Roof almost completely shingled, inside air conditioning/ductwork
installed, cat5 telephone wiring installed, heavy duty wiring (hot tub, waste
management system, stove, hot water heaters) installed.
May 10 - tubs and showers installed, all wiring completed and ready for the
final inspection. Security system installed.
May 13 - Roof completed, tabs put on to hold brick to walls. Inside
completed and ready for insulation and drywall.
May 14 - Drywall delivered, electrical inspection complete
May 15 - Pre-insulation inspection complete, doors installed, concrete for bricks delivered,
chimney cap installed, structured media center (SMC) installed, cat5 wiring
installed and run to SMC, phone and cable wiring rerouted to SMC, and speaker
wire installed in multimedia room.
May 16 - Sand delivered for bricking, insulation started, soundproofing mostly
complete.
May 17 - Rained out
May 18 - Garage insulated, soundproofing completed, scaffolding for bricking
delivered, pre-drywall survey performed
May 20 - Bricking one third completed, drywall half completed
May 21 - Bricking two thirds completed, drywall complete except for two garage
walls
May 22 - Bricking complete except for window eaves, fireplace, and mailbox;
drywall complete, taped and mudded.
May 24 - Bricking complete except for mailbox, all nail heads and flaws in
drywall mudded.
May 25 - Ceiling texture blown in, electrical feed run from transformer to
house, more drywall flaws found and marked for work
May 28 - Garage door installed, all inside doors, wood for shelves, closets, and
trim delivered
May 29 - All interior doors installed, drywall flaws fixed, texturing blown onto
walls
May 30 - All shelves (pantry, closets, etc.) installed, mantle added to
fireplace, most wood trim (molding, window sills) installed.
May 31 - No work today
![]() |
Here's the brick but it's hard to tell the color (reddish with some black) because of the way the sun hit it when I took the picture. (May 1) |
![]() |
A scan of one of the actual bricks that shows the color a bit better. Still just looks like a red brick though, doesn't it? |
![]() |
Front of the house after installation of the windows (left to right - bedroom 2, entryway door, dining room, utility room, garage (with the nicest looking windows - go figure), bedroom 3 |
![]() |
The garage and window in bedroom 3 |
![]() |
Back of the house (left to right - bathroom 3, outside door to bedroom 3, game room, dinette, outside door to dinette, multimedia room, outside door to master bedroom, master bedroom window, master bath window) |
![]() |
I had to adjust this photo because it was a bit dark but, from left to right - master bedroom windows, office (large square window), bathroom 2 (small window you can barely see below the eave) then back to the front. |
![]() |
Fireplace installed in game room (May 8) |
![]() |
The behemoth air conditioning unit (May 9) |
![]() |
Air conditioning lines, electrical, and phone lines in bedroom 3 |
![]() |
Here's a scan of a piece of one of the shingles |
![]() |
Roof mostly shingled |
![]() |
This is the wall between the master bedroom and master bath that I soundproofed. (May 18) |
![]() |
The wall between the mutimedia room and the office with soundproofing. |
![]() |
The wall between the game room and bedroom 3 after soundproofing installed |
![]() |
Structured Media Center box installed. Components will be installed after closing on the house. |
![]() |
Day one of bricking (20 May) |
![]() |
Drywall in master bath. Shower and tub can be seen in the photo |
![]() |
Game room wall with fireplace. Bedroom 3 is on other side of the wall |
![]() |
Kitchen as viewed from game room. Dinette is the open area to the right. |
![]() |
Bricking after day two (May 21) |
![]() |
Front of house |
![]() |
Beginning of fireplace, drywall taped and mudded (May 22) |
![]() |
Bricking complete (24 May) |
![]() |
Back of house after bricking complete |
![]() |
Garage door installed (28 May) |
![]() |
Fireplace with mantle (30 May) |