June
June 3 - Waste Management System installed, wood trim caulked. Closing
date set for 27 June
June 4 - Inside house prepped for painting, slab cleaned (chipped areas
filled, plaster "slop" removed)
June 5 - Worked too late to make it by the house
June 6 - Inside house woodwork, walls, shelves painted. Cabinets
delivered.
June 7 - Kitchen cabinets installed, attic insulated.
June 10 - Bathroom cabinets installed, cleanup begun around house, repair started on wall that was too
short and door that was too small.
June 11 - Kitchen countertops installed, some lighting installed, air
conditioning vents installed, security system installed.
June 12 - Most lighting, fans, switches, and electrical outlets installed,
dishwasher installed.
June 13 - Continuing work on electrical outlets, electric circuit breaker panel
completed, all linoleum installed.
June 14 - More lights installed.
June 17 - Door knobs, deadbolts installed. Remaining trim woodwork cut and
installed where linoleum was laid.
June 18 - Entryway tile laid, closet rods installed.
June 19 - Bathroom skinks and masonry trim installed, entryway grouted
June 20 - Outside trim painted, lot cleaned off.
June 21 - Toilets, kitchen sink, dishwasher, speaker wall outlets, phone and
CAT5 punch panels and wall outlets installed. Work begun on driveway and
walkways. Remaining woodwork caulked. Major cleanup effort begun
inside the house and garage. Closing date changed to "sometime the
first part of July".
June 24 - One of the water heaters installed, driveway paved. Final
walkthrough 3 July, closing set for 9 Jul.
June 25 - Screens installed, more cleanup work done
June 26 - Last toilet, plumbing, and carpet installed.
June 27 - Gutters and downspouts installed, second water heater installed, most
mirrors installed, about 10 loads of sand put in yard then leveled and
graded. Inside of house cleaned completely.
June 28 - Mailbox built, Master bath mirror, shower door, air conditioner compressor and electric meter installed.
Remaining lights and fan delivered.
![]() |
Sample of the countertop |
![]() |
Sample of kitchen and bathroom cabinets |
![]() |
Sample of the Kitchen, Utility Room linoleum |
![]() |
Bathroom linoleum |
![]() |
Waste management system installed. Can't really tell from the picture but, it's about 10 feet deep and is actually a smaller version of what most cities use. The trench tailing off to the right is a sprinkler system that goes to a couple of heads in the yard. The water is clean enough after going thru the system to be used to water the yard. (3 Jun) |
![]() |
Master bedroom after painting. The woodwork is gloss white, bathrooms are semi-gloss white, the rest of the walls are flat off-white (Ecru, I think). Ceiling is the blown "popcorn" stuff. (6 Jun) |
![]() |
Cabinets in master bathroom. You can also see the linoleum that's installed in all the bathrooms. Note that this is one of the split-level counter types. It'll be nice to not have to bend over to use the sink. |
![]() |
Kitchen cabinets installed |
![]() |
Master bedroom again only with the fan installed. Not really sure what they call the finish on the lights and fans. It's sort of a "distressed" copper color. (12 Jun) |
![]() |
Scan of a piece of the entryway tile. |