Town of Boone Project Updates
Water
Engineer Study evaluating raw water alternatives: Complete
Environmental Assessment of preferred options (which is required for permitting purposes) : Complete
The Town is in the process of looking for a suitable site to meet our water needs
Study is available for public inspection at Town Hall
Greenway Expansion
Plan to extend Greenway from behind Hunam to Faculty Street
This section will be along Greenway, Winklers Creek and Wilson Road and will include bike lanes and sidewalks
This project will be done in four phases due to cost considerations
The first phase will include the section along Wilson Road
Town has a DOT enhancement grant to help cover the cost of this phase
Town waiting for final DOT approval of most recent submitted plans
Project will then be submitted for bids
Howard Street
Progressed from the concept developed 8 years ago to adopting the design
In the process of acquiring needed voluntary easements (done to contain the costs) then we will move to the construction phase
Per the recommendation of the Local Government Commission the Town will pursue an installment purchase loan to finance the project
421 Project
Town working with DOT on enhancements to the 421 Project
Town working with the County and ASU on moving the 421 Project up on the priority list
SMART Growth Audit
Audit is in process, stakeholders to be interviewed
Completed by December 2007