March 8, 2005—The construction phase is officially done, and the house is mortgaged. This does not mean that we are done with the house, but it does mean that the city is done with us. They have signed off on the project, and thus for the first time in nearly thirty years the Farm House is a legal residence.
Obviously, much has happened since last I wrote. The windows are all now operable and lockable. The electrical work has been completed, and the permanent connection to the electrical lines made. The mantelpieces have been put back in place, and our foreman has built a replica mantelpiece, exact in every detail but without the spoon carvings, to replace the missing one in the parlor. He has also miraculously resurrected the horribly damaged front door. All exterior wood is primed. The kitchen needs only the finish coat of paint on the walls, stain and varnish on the cabinets and woodwork, and grout on the backsplash tile to be complete. Both bathrooms are fully functional. The driveway is installed, and the walkways poured. Telephone, network and cable wiring are all complete and ready to be hooked up to the outside world. The gutters are up. Also, the fence between the front and back yards is complete. It has been an eventful five months.
The work went very slowly at first, because of
the sheer size of the
downstairs windows, and also
because it took several weeks for me to figure out how to remove some
exceedingly stubborn and
granite-hard 116-year-old glazier's putty. Once I had finished the four
downstairs side windows,
however, the rest of the windows went fairly quickly. It helped matters
for me that the foreman and
finish carpenter did a lot of the work on the second floor. The sills
of all the windows to the rear of
the second floor were shot, but the timbers were okay, or rather, the
casings were otherwise usable,
so the finish carpenter removed them, took them apart, then reassembled
them with new sills. We
had to replace the sash in five of the six dormers, which the foreman
and finish carpenter installed.
Their work made my job much easier.
I left the bay window for last, because it
appeared that there would be
some problems, and I
wanted to have as much experience as I could before tackling them. The
side windows are double-hung and non-operating, but the original method
of fixing the lower sash had disappeared, and
they were simply nailed in place. Moreover, the sash lock of the center
window had been mortised
deeply in to the top rail of the inner sash, indicating an alignment
problem that was not
immediately apparent. Happily, by the time I got to them I was firing
on all three cylinders
window-wise, so I was able to address these problems in short order.
Late one Tuesday evening, the
last remaining boarded-up windows were ready to be uncovered.
What a marvelous transformation was brought about by the
opening of
those huge, door-sized
windows! Suddenly, the first floor was a bright, airy place. For the
first time, I could appreciate the
dramatic views of the mountains from the north rooms. For the first
time, I could see how the light
reached into every nook and cranny of every room. For the first time, I
could see clearly just how
thrashed the interior is. The electrical work was finished at about the
same time, which really put
the exclamation point on my enlightenment.
It was satisfying to see how well my electrical
layout—fixture, switch
and outlet location—works.
My Dad did the electrical layout for a home built for the family up in
the Willow Glen area of San
Jose before I came along, and he used to tell me with great pride how
he had carefully laid things
out so that outlets and light switches were everywhere they might be
needed, so that one would
never trip over a stretched cord, nor have to cross a darkened room to
turn the light on. This was
years before electrical codes began to reflect these considerations. By
this example, Dad taught me
that any job worth doing is worth doing well.
As I mentioned, both bathrooms are now fully functional.
Bye-bye, Andy
Gump! The downstairs
bathroom has its medicine cabinet, built by the people who built the
kitchen cabinets. The room
still needs to be painted, and some hardware still needs to be
installed, but everything works. I've
lived in places where the entire bathroom was smaller than that shower
stall. It's not fancy by
current standards, but it is roomy. The upstairs bathroom is in service
as well, and it still needs
painting, although I have done some of the finish painting already. As
I've mentioned, we're
restoring this bathroom more or less as we found it, in Victorian
style. This means that the floor
and walls around the fixtures are visible, so I needed to finish them
before the fixtures were
installed.
This turned out to be a pretty tall order, because even
after the
contractor was done with the room
it was still in a pretty bad condition. The beadboard wainscoting was
in awful
shape, and the drywall work,
skilfully executed elsewhere, was shockingly sloppy wherever it met
wood. Also, this is the one
room in the house that did have dozens of coats of paint applied, and
one of the earliest coats had
been cracked all over when it was painted upon. Everything needed
stripping, including the floor,
but I didn't have the time because the plumber was waiting for me to
finish, and after starting to
strip the beadboard I found that it takes a very long time to strip it
without ruining the beads. We
really should have replaced all the beadboard in that room, but to be
honest this was the one room
I hadn't thought out fully. There were too many variables, and I
couldn't form a clear mental
picture of it in completed form, so I deferred those plans until after
I saw the walls redone. Big
mistake. I was faced with a real mess, and not much time in which to
fix it.
So I stripped the items that absolutely had to be done:
the window
casing, the floor, and one
beaded trim piece that was cracked in several places and needed
delicate surgery without its being
removed. For the rest, I tried an experiment. Abatron Citrastrip is a
stripper that is very effective
but rather slow in its effect, so I figured I could time it so that it
would just strip the first coat off
and soften the next coat a little. This worked very well; it filled in
the cracks, made the paint easy
to sand, and greatly lessened its tendency to chip and flake off. If I
hadn't done this it would have
been impossible to make the beadboard look good without stripping it
completely.
By the way, in the process I discovered clues that prove
beyond a
reasonable doubt that the
bathroom had always served as a bathroom, but that it was plumbed some
time after the house
was built. An explanation of the clues would be long and boring, but
they mostly have to do with
paint patterns. One detail I will relate is that there was an
upside-down L-shaped area that was
unpainted at the level of the first coat, and this L bounded a rather
obvious patch in the
beadboard that stretched from the floor to about 18 inches up. This
most likely was where a built-in chamber pot stood. And guys complain
today about taking out the garbage.
After performing my reamalgamation experiment on the
beadboard and
stripping the floor, I
completed the painting behind and underneath where the fixtures were to
go,
leaving the rest for later.
Lydia stripped, sanded and painted the outside of the tub; she did a
superb job, certainly better
than I could have done. She found a new set of tub feet using my
casting, and our friend Gary, who
has all sorts of handy connections through his work, had them
nickel-plated for us. The shims
needed to affix the feet firmly to the tub were missing, so the foreman
and his assistant fabricated
new ones. All put together, with the new faucet and shower, it looks
great.
Other than the inexpensive modern toilet we put in
temporarily while I
restore the original, the only
completely new fixture in the upstairs bathroom is the vanity. We
wanted a undermounted basin
with a marble top and nickel legs, but complete vanities fitting this
description are exorbitantly
expensive, so we assembled ours from several sources. The people who
built our kitchen cabinets
and installed the granite counters made the marble top and backsplash
for us, and we're deliriously
happy with the result. It's thoroughly Late Victorian.
Speaking of the kitchen cabinets, we're happy with those,
too, although
it was quite a struggle to
get them built the way we wanted them, and they ended up much fancier
than I had originally
envisioned. I drew up precisely-dimensioned diagrams (called
"elevations") for them which the
architect included as part of the approved working plans, so I expected
that our desires were
perfectly clear in this regard. I designed simple face-framed flush
front cabinets with framed doors
and slab drawers, cabinets of a traditional design that I've seen in a
hundred homes. They were to
be custom-built to fit the space most efficiently, but otherwise they
were modest, paint-grade
cabinets.
I did not know at the time that no one builds cabinets
like these
anymore, because they require
actual cabinet-making skill to build. The guy our contractor wanted to
use came up with a design
that used standardized cabinet sizes and cheesy non-mortised hinges; it
bore only a passing
resemblance to my design. We could have done better at Home Depot.
Finding someone willing to build the cabinets our way
proved to be as
difficult as it was to find an
architect for the project. With unrelenting determination, however,
Lydia finally tracked down
someone willing to do it our way. In the process, however, my simple
paint-grade cabinets became
stained-and-varnished maple. In fact, the entire look of the kitchen
was upgraded once a solid
image of its completed form coalesced in Lydia's mind. I was going for
a mid-30s sanitary look, all
bright white and chrome, because at the time I came up with the plans I
wanted a kitchen that was
practical, modest, and easy to clean. I had an aversion to the kind of
museum-like kitchens one sees
in architecture and design magazines with $100,000 in cabinetry and a
similar amount in
appliances, open bookcases, hanging plants and the like. Anyone can see
that no one who actually
uses a kitchen to cook and bake on a regular basis could keep such a
kitchen clean without a full-time maid to clean the grease off the
books and plants regularly.
Happily for our house, Lydia had more imagination than I.
She saw some
middle ground between
classical and rococo, and as a result the casings, windows and doors
will be stained and varnished to
match the rest of the house, the oak plank floor stained somewhat
darker than natural, and the
cabinets stained somewhere in between. The walls have gone from pure
white to something a tad
warmer, but not enough to suggest anything besides white (to paraphrase
Mrs. Blandings).
Although these changes entail more work than I had originally planned,
I am happy with them,
because I was not looking forward to covering all that pretty redwood
and maple
with paint.
Moreover, the transition between old and new will now be much smoother,
and the kitchen far
more comfortable to be in without being appreciably more difficult to
maintain. I only wish she had
made the changes before I primed the windows and exterior doors.
Virtually all of the concrete work is done,
and the driveway is in. The
driveway, paved with
decomposed granite, has proven to be the most controversial feature of
the restoration. It was a lot
of work for the contractors, in the grading and also in simply finding
a source for the right kind of
paving material, and neighbors have questioned both the practicality of
the material and the width
(eight feet) of the driveway. Both these points have some validity, but
we are happy with the
driveway nonetheless. If it had been wider, we would have to have taken
out more trees, and as I
have mentioned, we were unwilling to do this. The decomposed granite
allows percolation of water
into th
e earth, which greatly lessens the impact of
the driveway over
anything nonporous. The
width is adequate, is properly scaled to the house, and provides an
infallible sobriety test: anyone
who cannot make it down the driveway is in no condition to drive.

Still, there is no way around the fact that the Farm House
will always
be a high-maintenance
property, largely because of all the debris generated by the trees. In
some respects this debris is
valuable; people pay good money hereabouts for pine-needle mulch and
oak-leaf mold.
Nevertheless, even pennies from Heaven can be a nuisance in the wrong
place. One odd task that I
have found I must do on a monthly basis is the sweeping of the roof to
remove the accumulation of
leaves, pine needles and miscellaneous tree dandruff. If the debris is
allowed to pile up, eventually
the roof becomes a big compost heap, especially with all this rain
we've been having. One would
think that the steep roof pitch is sufficient to eject this junk, but
it isn't. On the other hand, I have
found it is plenty sufficient to eject me If I'm not very, very
careful. I'm thinking of getting some
rappelling equipment, or perhaps a parachute.
After the driveway came Christmastime, and
after that the building of the fence separating the front and back
yards.
I designed the fence
hurriedly one weekend towards the end of the design phase, when our
architect suddenly informed
me that he needed my fence elevations post-haste for inclusion in the
plans. I had a vague idea
floating around in my head based upon a fence I had seen in a movie
(old movies are a great place
to get design cues), but this would have been too ornate for the
committee to approve, because
they don't want new design elements to emulate period designs too
closely. I thus had to streamline
the design while keeping it harmonious with the house. This was a tall
order for one who cannot
draw a straight line, or for that matter a curved one.
Our foreman addressed the building of the fence as he does
everything,
that is, with great care and
thoroughness. He very carefully took the measurements from my
elevations, laid everything out,
and even built a scale replica of one of the gates to work out the
details. He eschewed the
dimensional lumber for the pickets, choosing instead to mill his own
pickets to ensure each one was
straight. He beefed up my specifications for the post construction,
replacing my steel poles with
quarter-inch thick steel beams sunk four feet into the ground.
As built, the design proved to be a great success in every
regard. It
is very efficient in its use of
material, requiring almost no waste in terms of leftover wood. The fill
is very light, which in
combination with the massive posts means that this fence will never,
ever sag. There is absolutely
no flex nor play in the structure; I threw all my weight against it as
a test, and all I got was a sore
shoulder: the fence remained motionless. The response from the
neighborhood was immediate and
uniformly positive. It was a grand fence, befitting a grand house. But
there was one little problem.
They hadn't, but the fact is that our architect had noted
"6' 0" fence"
right on his map of the lot.
Now, he could be expected to take a ruler to everything, and
so he must have known that my design
was over six feet. But he said nothing. He didn't even add a note to
this effect on the page
containing my elevations of the fence. Our contractor had circled the
fence and made his own
notation on the approved set of plans, but no one ever works from this
set of plans, which are kept
in a safe place for inspection. The foreman didn't see the printed
notation because he was working
from my elevations. So no one noticed that the fence was too high until
the inspector enlightened
us.
At first I thought, "Well, this is no problem. The fence
does not
violate the spirit of the law, and
city officials misled us regarding its suitability. I'm sure that we
can work this out." But this was not
a fight we could win, and so I was faced with the galling task of
deciding what to hack off where in
order to bring the fence into compliance. I hate having my work edited
according to
someone else's parameters,
but if it must be done I'd rather do it myself.

The result still looks fine. The foreman did his usual
miracle job, so
no one will ever know that the
fence was ever different, or that it is wildly out of proportion. But
I'll know.

We've chased down most of the hardware we
need, and whenever I have a
spare moment I attend
to the large pile of brass, nickel and iron—taking inventory, sorting
it out, rehabilitating it. I
especially enjoy the last activity. I find it quite satisfying to take
an old lockset, bent from use, choked with rust
and blackened with tarnish, and make it shiny and functional again.
It's a tribute to Victorian
applied science to see how well those Niles mechanisms have held up to
a century of abuse. Here
and there I find a broken spring, but for the most part all I have to
do is clean them up and
lubricate them to have them functioning perfectly again, smoothly and
quietly, with no adjustment
needed.
I was sitting in the dining room sorting out
hardware the other day
when I noticed a piece of
sandpaper that the floor guy had left lying on the floor face down
(ahem!). What attracted my
notice was a statement printed on the back: "The color PURPLE is a
trademark of 3M." Wow.
That must be a hard one to enforce.
In a house and garage with 31 windows and 30
doors, hardware is one of
the major matters of the
project, especially considering that most of the hardware was missing
when we acquired the place.
It's a huge job even to keep track of everything we need, to say
nothing of acquiring, refinishing
where necessary, and installing it. I am fortunate to have had some
able help on this front. Our
foreman has been invaluable in telling me exactly what hardware we need
for applications with
which I am unfamiliar, such as the double casement windows and the
pass-through doors. Lydia, a
master of shopping kung fu, has managed to dig up everything I've asked
her to, no matter how
obscure the piece. She's also learned how to work a buffing wheel, and
has been a great help in
polishing the brass pieces.
Special Farm House kudos go out to our friend
Gary and his boss Joe. In
their line of work they do
a lot of metals casting, plating and finishing, and they are also both
old-stuff enthusiasts. We were
having a hard time finding all the Niles escutcheons we needed (40 or
so) at a remotely reasonable
price. Liz's had plenty, but at a price that, with all due respect to
that fine and indispensable
establishment, was about twice what they are worth. We had managed to
get about a half-dozen of
them, and were beginning to go farther and farther afield to find more,
when Gary suggested that
we might have our own cast in brass for a reasonable price. We took him
up on his offer, and he
and Joe took a great deal of care in getting the job done well. We
ended up with beautiful
reproductions cast in the high-quality lost wax method, polished and
clear-coated, for much less
than we would have paid for originals that we would still have had to
buff and lacquer. They also
plated the tub feet for us, as I mentioned above. For their meritorious
service, they are hereby
added to the rolls of the Friends of the Farm House.
As I mentioned above, the foreman performed a miraculous
resurrection
of our front door, which
was horribly and seemingly irreparably damaged by a vandal one
Thanksgiving several years back.
The rail on the latch side was broken off, a panel cracked, and some
molding and fill pieces
destroyed. Even the contractor was convinced that the door was
unsalvageable. But our foreman
long ago took the admonition to keep as much original material as
possible to heart, and so he took
the time and care to perform breakthrough, life-saving surgery on the
door. He set the broken
panel, performed a rail transplant, replaced the exterior molding, and
milled the remaining pieces
himself. The result, when the door is refinished, will be visually 100
per cent indistinguishable from
the original. He did similar work on an interior door that had been
damaged during the demolition,
with similarly miraculous results.
He also constructed the pass-through doors to match the
look of the
passage doors on the dining
room side and the cabinet doors on the kitchen side. All the gaps are
perfectly straight and at a
minimum. When they're stained and varnished, they'll look as if they've
always been there.
He did a remarkable job of building the replica
mantelpiece as well.
This was as usual a task that
required a great deal of good judgment, because each of the three
existing mantelpieces is a bit
different from the others, and all four are of slightly different
dimensions. This was thus more than
a mere copy job. The one thing he was unable to do is replicate the
spoon carving, for this is a very
specialized skill using special tools and is not satisfactorily
reproducible using any other method. I
have no doubt that he is capable of the work, but time was a fatal
limiting factor in this regard.
This is just as well, for it is common practice in restoration when
replacing a missing element to do
something to indicate that it is not original. This achieves that goal
elegantly. There is still much
cosmetic work to do on the original insert pieces, but the fireplaces
are otherwise functional.
The gutters were completed a scant hour before a major
week-long deluge
let loose, a storm that
put this rain season in the history books as the third wettest since
1867, when official weather
statistics were first recorded. This makes it the wettest winter anyone
currently alive has ever lived
through in Los Angeles, and the second-wettest the Farm House has seen.
Its wettest was the
winter of 1889-90, when it was just a year old. So much for global
warming. I am very happy to
report that the Farm House has come through with flying colors, with
not a drop of rain intruding.
I have primed all the new exterior wood. I discovered
while painting
the upstairs bathroom that
even though the paint I am using is very good, with the deep colors
involved it sometimes takes
three coats to achieve complete coverage over white primer. So, I got
some pigments and made up
some primers tinted to be close to the trim finish colors, green and
dark red. Where you see those
colors in the pictures, that is where the green and red will go, but
where you see white it could be
any color, because at certain points I was too busy to stop to tint
more primer. It is a slow, messy
job.
It has proven a useful exercise nonetheless, because it
has really
helped me understand complicated
Victorian color theory, and it has given us the freedom to try out our
ideas on the house before we
spend a lot of money on the finish paint. It confirmed that my scheme
for picking out parts of the
porch posts in the second trim color works well. It also helped to
convince us to go back to
something closer to our original paint scheme, which used darker, more
reddish body colors: a
medium-toned reddish brown for the body color instead of mustard yellow
and tan for the shingled
gables instead of beige. We lightened the body colors because we were
afraid of making the house
seem too small, but seeing how the darker trim colors work in the
actual light indicated that our
original colors were more appropriate. I'm currently doing some color
studies so that we can zero in
on just the right shades.
I have also gotten a clear idea of just how
big a job the painting of
the house will be, especially the
second story. The peak of the roof is 24 feet high, and dangling from a
ladder with a wet paintbrush
in your hand gets unnerving after a while. I learned this while priming
the south bargeboard. I was
fine, completely at ease up there, until I got past the peak and
started down the other side.
Suddenly, instead of looking up I was looking down, and I lost my
nerve. It's not that I am afraid of
the height per se; what gets me is the realization that one false step
and I'm painting the ground
red. But the worst that happened was that I dropped the brush in the
paint, making it a bear to
clean later.
The dormers were tough at first as well, but the foreman
showed me a
neato way to make the job
safer and easier, if not exactly easy and safe: one lays an extension
ladder along the roof line,
extending it down to the ground. Then he drives a stake in to keep the
ladder from sliding. The ladder then becomes a foothold to keep one
from sliding off the roof
while painting the dormers.
This worked for the side eaves of the garage as well, where the
rooflines diverge at the rear
extension. 
There are some areas here and there on the house where I
have already
applied the finish paint: the
fascia boards and trim behind the gutters and the moveable sash in the
rear dormers. In fact, these
sash are finished on the inside as well, stained and varnished to match
the existing interior finish.
Later on I'll rub out the varnish in order to even out the sheen, but
for now I'm done with them.
When I look at the Farm House I see what the house is
going to look
like when it's done. But
neighbors and frequent passers-by see it differently. For as long as
most of them can remember, the
house has been a derelict, a boarded-up eyesore with a collapsing
veranda. Then, they saw the
veranda get torn down, and they had no idea what would happen. From
then on, the original house
has rematerialized piece by piece, and now it is all back as they
remember it, except everything is all
nice and straight and complete. In the words of one of the neighbors, a
nice lady with a sweet
daughter and a great dog who reminds me of our Nellie, "It's like
watching the house being reborn."
From the beginning, it was common for cars to slow down a bit to look
as they drove by. But as
more windows were uncovered and more wood painted, the slowing became
increasingly
pronounced until, once the bay window was open, cars started coming to
a dead stop. This
unnerved me at first, but I'm beginning to get used to it. She's a real
looker.